Terry
Published on 25 September 2011

MLK, GRAND AND 7TH
Installation of Overhead Catenary Electrical Hardware and wire from NE Broadway to SE Stephens on MLK, Grand and NE 7th
Weeks of Oct 24, Oct 31, Nov 7, Nov 14
- THESE WIRES SHOULD BE CONSIDERED “HOT” WIRES AS SOON AS THEY ARE INSTALLED. Please inform vendors, delivery vehicles and maintenance personnel that all activities must take place at least 10 feet from live power lines. Work closer than 10 feet must comply with OSHA safety requirements. These referenced activities could include, but are not limited to, painting, maintenance work, garbage removal, recycling, tree trimming, etc.
- The parking lane and up to one lane will be closed from 7:00AM to 5:00PM Monday thru Friday.
- Bicycle and Pedestrian access will be maintained
Sidewalk Improvement from Lloyd to Davis on NE MLK
Week of Oct 24
- One lane will be closed on MLK from 7:00AM to 4:00PM
- Bicycle and Pedestrian access will be maintained.
Sidewalk Improvement and Storm Water Planter work at Morrison, Belmont and Hawthorne on SE MLK
Weeks of Oct 24, Oct 31, Nov 7, Nov 14
- The left lane will be closed on MLK from 7:00AM to 4:00PM
- Bicycle and Pedestrian access will be maintained.
Signal Activation at Clay on SE MLK
Week of Oct 24
- The signal will be turned on at this location.
- One lane will be closed on MLK from 7:00AM to 4:00PM.
- Traffic will be maintained with flaggers.
- Bicycle and Pedestrian access will be maintained.
Permanent striping of crosswalks from SE Stephens to NE Broadway on Grand & MLK – WEATHER DEPENDENT
Weeks of Oct 24, Oct 31, Nov 7
- Up to two lanes will be closed from 9:00AM to 6:00PM.
- Bicycle and Pedestrian access will be maintained.
Signal Activation at Hawthorne on SE Grand
Week of Oct 24
- The signal will be turned on at this location.
- One lane will be closed on Grand from 9:00AM to 6:00PM.
- Traffic will be maintained with flaggers.
- Bicycle and Pedestrian access will be maintained.
Sidewalk and Signal work from Hawthorne to Alder on SE Grand
Weeks of Oct 24, Oct 31
- One lane will be closed on Grand from 9:00AM to 6:00PM.
- Bicycle and Pedestrian access will be maintained.
Electrical work from Lloyd to Holladay on NE Grand
Weeks of Oct 24, Oct 31, Nov 7, Nov 14
- Parking and one lane will be closed on Grand from 9:00AM to 6:00PM.
- Bicycle and Pedestrian access will be maintained.
Sidewalk improvement at Oregon on NE 7th
Week of Oct 24
- Parking will be closed on 7th from 7:00AM to 4:00PM.
- Bicycle and Pedestrian access will be maintained.
Platform Construction at Halsey on NE 7th
Week of Oct 24
- NE 7th will be closed to northbound motorized vehicle traffic from Wasco to Halsey from 7:00AM to 4:00PM.
- Parking will be closed on 7th.
- Bicycle and Pedestrian access will be maintained.